STEELHART Fabrication Co.
Back to Tech PortalSH-MRU-IOM-2026 · TECHNICAL DEPLOYMENT PORTAL

Modular Restroom Unit
Installation & Operation Manual

A guided, interactive walkthrough of the installation and operation manual. Use the navigation to move through each deployment stage — from site utilities to commissioning and maintenance.

00

Safety & Site Placement

Read Before Deployment

Read this manual before connecting utilities or placing the restroom into service. Installation, electrical, plumbing, HVAC, lifting, and transport work should be performed by appropriately qualified personnel in accordance with applicable local codes.

Site Placement

Place the container on a stable, adequately supported, reasonably level surface. Maintain access to doors, the rear service area, utility connections, and HVAC openings. Do not position obstructions where they restrict required access or airflow.

Utility Safety

Disconnect electrical power and shut off the water supply before servicing. Do not modify factory-installed electrical or plumbing systems or bypass safety devices. Never energize an empty or partially filled electric water heater.

01
SH-MRU-OVW

Unit Overview

The Modular Restroom Unit is a 20-foot containerized restroom facility engineered for high-traffic, long-duration deployment. Equipment, fixture quantities, and configurations may vary by floorplan.

Unit Overview — figure 1
FIG.01Modular Restroom Unit — exterior three-quarter view
Unit Overview — figure 2
FIG.02Exterior side view, rear double-door service access, example restroom interior, and waterless urinal configuration
Configuration Notice

Equipment, fixture quantities, electrical circuits, plumbing connections, and equipment locations may vary depending on the specific restroom floorplan, options, and configuration. Photographs and diagrams in this manual may illustrate an example configuration. Always refer to labels and equipment installed on the specific unit.

Container Length20 feet
StructureSteel shipping container
AccessRear double-door / service area
ConfigurationsRestroom, waterless urinal, combo
02
SH-MRU-UTIL

Site Utility Connections

Before placing the restroom into service, the customer must provide and connect the required site utilities. Final requirements may vary depending on configuration, site, and locally adopted codes.

Site Utility Connections — figure 1
FIG.01Exterior utility connection area — 240V/50A power inlet, 1-inch water inlet, 3-inch wastewater outlet
Site Utility Connections — figure 2
FIG.02Example electrical panel and rear service area — equipment and manifold configurations may vary
Power Inlet240V / 50A
Water Inlet1-inch
Wastewater Outlet3-inch

Recommended Utility Connection Sequence

  1. 01
    Wastewater

    Connect the 3-inch wastewater outlet first. Verify support, continuous 1/4-inch-per-foot fall, and unrestricted drainage.

  2. 02
    Water Supply

    Connect the 1-inch water inlet. Verify 40-80 PSI, slowly pressurize the system, and inspect for leaks.

  3. 03
    Fill Water Heater

    If the heater will be used, place the bypass in normal operation and confirm the heater is completely full.

  4. 04
    Electrical Power

    After wastewater and water systems are verified, connect the supplied 240V / 50A shore cord.

  5. 05
    Commission Unit

    Test fixtures, drains, lighting, HVAC, water heater, and other installed equipment.

Critical — Water Heater Dry-Fire

DO NOT energize the water heater until it is completely filled with water and a steady, uninterrupted flow has been verified at the lavatory faucet. Energizing an empty or partially filled heater can damage the heating element.

2.2 Wastewater / Sewer Connection

Connection Size3-inch
Connection TypeGravity wastewater / sanitary drain
Recommended Slope1/4 inch per foot
Final Site ConnectionCustomer provided

The customer is responsible for providing the wastewater piping and equipment between the restroom outlet and the site sanitary sewer, external lift station, or other approved wastewater system. Install horizontal gravity piping with a continuous 1/4-inch-per-foot fall toward the approved discharge point. Avoid backfall, low points, and unsupported sections. The final connection should be designed and installed by a licensed plumber.

Before Placing the Wastewater System Into Service

0/9

2.3 Fresh Water Supply Connection

Connection Size1-inch direct water inlet
Operating Pressure40-80 PSI
Pressure RegulatorNot factory installed
Main ShutoffCITY FILL valve (rear service area)
Final Site ConnectionCustomer provided

Maintain approximately 40-80 PSI during normal operation. Use appropriately sized piping, hose, fittings, and connections. Provide a suitable pressure regulator when site pressure could exceed 80 PSI. Provide backflow protection where required by applicable plumbing code. The main incoming water shutoff is labeled CITY FILL and is located in the rear service area above the water distribution manifold.

Before Placing the Water System Into Service

0/8

2.4 Water Heater Initial Fill

Dry-Fire Damage

The water heater must be completely filled with water before electrical power is supplied. Energizing an empty or partially filled water heater can damage the heating element.

Initial Fill Procedure

  1. 01
    Verify Supply

    Verify the restroom water supply is connected and the CITY FILL valve is open.

  2. 02
    Set Bypass

    Place the water-heater bypass valve(s) in the normal water-heater operating position.

  3. 03
    Open Faucet

    Open/activate the lavatory faucet.

  4. 04
    Clear Air

    Allow water to flow until a steady, uninterrupted stream is present and trapped air has been cleared.

  5. 05
    Inspect

    Inspect the water heater and accessible piping for leaks.

  6. 06
    Energize

    Only after the heater is confirmed full, supply electrical power to the water heater.

2.5 Electrical Power Connection

Electrical Service240V / 50A
PhaseSingle phase
Connection50A RV-style shore-power system
Supplied Cord25-foot, 240V / 50A shore cord
Final Site PowerCustomer provided

The customer is responsible for providing a suitable site electrical source and compatible outdoor-rated receptacle. If the site is not already equipped, a licensed electrician should provide the required service in accordance with applicable local electrical code.

03
SH-MRU-WTR

Water Distribution System

The water distribution manifold routes supply water to each fixture through individually valved branches. The manifold is located in the rear service area.

Water Distribution System — figure 1
FIG.01Water distribution manifold — CITY FILL main shutoff and individually valved fixture branches
Manifold LocationRear service area
Main ShutoffCITY FILL valve
Branch ValvesIndividual fixture shutoffs
Operating Pressure40-80 PSI

Each fixture branch is valved at the manifold, allowing individual fixtures to be isolated for service without shutting down the entire system. Manifold configuration and labeling vary by floorplan. Verify valve labels against the installed unit before servicing.

Routine Verification

0/4
04
SH-MRU-LAV

Lavatory & Water Heater

The lavatory is served by an under-sink electric water heater with a bypass valve arrangement that allows the heater to be isolated for service.

Lavatory & Water Heater — figure 1
FIG.01Under-sink 2.5-gallon water heater and plumbing configuration — actual arrangements may vary
Lavatory & Water Heater — figure 2
FIG.02Under-sink water heater and Delta 87T105 single-temperature metering faucet installation
Heater TypeElectric tank
Capacity2.5 gallons
LocationUnder lavatory
BypassHeater bypass valve(s)

The water heater provides on-demand hot water to the lavatory faucet. The bypass valve allows water to flow to the faucet even when the heater is isolated for service or replacement. Always confirm the heater is completely full before energizing.

Heater Isolation

When placing the bypass in service position, confirm the heater is full before restoring power. Never energize an empty or partially filled heater.

05
SH-MRU-FIX

Restroom Fixtures

Fixtures vary by floorplan and may include flush toilets, waterless urinals, and lavatory sinks. All fixtures are commercial-grade and engineered for heavy daily use.

Restroom Fixtures — figure 1
FIG.01Restroom fixtures — lavatory/sink area, toilet stall configuration, and Sloan WES4000 waterless urinals
ToiletsCommercial flush
UrinalsWaterless (if equipped)
LavatorySink with faucet
ConfigurationVaries by floorplan

Flush toilets are served by the building water supply and drain to the 3-inch wastewater outlet. Waterless urinals, when equipped, drain by gravity to the same wastewater system and require no water connection. Fixture quantities and locations vary by floorplan — always refer to the installed unit.

06
SH-MRU-HVAC

HVAC System

The HVAC unit provides heating and cooling to maintain interior comfort. The wall-mounted unit is controlled by an interior thermostat.

HVAC System — figure 1
FIG.01Exterior HVAC installation and condenser/service compartment
Unit TypeWall-mounted HVAC
ControlInterior thermostat
Power240V / 50A circuit
Filter AccessFront panel

Set the thermostat to the desired mode (heat or cool) and temperature. The filter is accessible through the front panel and should be inspected and cleaned regularly. Maintain clearance around the exterior condenser opening — do not position obstructions where they restrict airflow.

HVAC Verification

0/4
07
SH-MRU-START

Initial Startup / Commissioning

After all utilities are connected and verified, commission the unit by testing every installed system before placing the restroom into normal service.

Commissioning Sequence

  1. 01
    Verify Utilities

    Confirm wastewater, water, and electrical connections are complete and verified.

  2. 02
    Test Fixtures

    Operate each toilet, urinal, and lavatory. Confirm flush, drain, and flow.

  3. 03
    Check for Leaks

    Inspect all accessible plumbing connections and the manifold.

  4. 04
    Test Water Heater

    Confirm heater is full, then energize. Verify hot water at the lavatory.

  5. 05
    Test HVAC

    Run heating and cooling cycles. Confirm thermostat response.

  6. 06
    Verify Lighting

    Confirm all interior lighting operates.

  7. 07
    Sign-Off

    Document completion and place the unit into service.

08
SH-MRU-WINT

Winterization & Freeze Protection

Freezing temperatures can damage plumbing, tanks, and fixtures. Freeze-protected units are engineered for cold climates, but shutdown in freezing conditions requires proper winterization.

Heat-traced supply lines, insulated tanks, and heated interiors protect the system during operation. If the unit will be shut down in freezing conditions, the water system must be drained and protected to prevent damage.

Winterization Checklist

0/6
09
SH-MRU-MAINT

Preventive Maintenance

Regular maintenance preserves performance, extends service life, and prevents costly failures. Follow the schedule below for routine care.

DailyClean and restock
WeeklyInspect fixtures, check for leaks
MonthlyHVAC filter, water heater check
QuarterlyFull system inspection
AnnualComprehensive service

Daily cleaning and restocking keeps the facility serviceable. Weekly inspections catch leaks and fixture issues early. Monthly HVAC filter checks maintain airflow and efficiency. Quarterly and annual inspections should be performed by qualified service personnel.

10
SH-MRU-MOVE

Shutdown & Relocation

When a project ends or the unit is redeployed, follow the shutdown and relocation procedure to protect the unit and prepare it for transport.

Shutdown & Relocation Sequence

  1. 01
    Winterize

    If freezing conditions are possible, complete the winterization checklist.

  2. 02
    Shut Off Utilities

    Disconnect shore power, shut off water at CITY FILL, and cap wastewater.

  3. 03
    Drain Systems

    Drain water heater, lines, and traps as required.

  4. 04
    Secure Interior

    Secure fixtures, close doors, and lock access points.

  5. 05
    Lift & Transport

    Use appropriate lifting equipment and transport per container guidelines.

11
SH-MRU-TROUB

Troubleshooting

Use the guide below to diagnose common operational issues. If the issue persists, contact SteelHart support.

ProblemLikely CauseAction
No water flow at fixturesCITY FILL valve closed or low site pressureOpen CITY FILL valve; verify 40-80 PSI at supply
Water heater not heatingHeater empty, no power, or tripped resetConfirm heater is full; verify power; press reset button
HVAC not runningNo power, thermostat setting, or clogged filterVerify power; check thermostat; clean or replace filter
Wastewater backupInsufficient slope or blockageVerify 1/4-inch-per-foot fall; clear blockage; check cleanout
Fixture leakLoose connection or failed valveTighten connection; isolate at manifold; replace valve if needed
12
SH-MRU-PARTS

Replacement Parts & Documentation

Replacement parts and equipment documentation are available through SteelHart. Maintain records of installed equipment and service history for warranty and support.

Each unit ships with equipment documentation for installed components — water heater, HVAC, fixtures, and electrical devices. Retain these documents for reference. For replacement parts, contact SteelHart with the unit spec code and a description of the required component.

Parts SourceSteelHart Fabrication Co.
Contact+1 (574) 403-8799
Emailsupport@steelhartfab.com
DocumentationRetain shipped equipment manuals

Need Support on This Deployment?

Our engineering team is available to walk through installation, commissioning, or any technical question on this unit.

Contact Engineering